Rural Access and Mobility Project-2 is a co-sponsoring project of the World Bank, the French Development Agency and Adamawa State Government through its counterpart funding to rehabilitate and construct roads in rural communities for boosting of social and economy activities of the local people in the state.
RAMP-2 is indeed doing a great work by consolidating and supporting the effort of the Adamawa State Government on roads construction, rehabilitation and maintenance as there are hundreds of communities being linked up with good access roads.
Lot 1 of the ongoing work is positively affecting the economy life of the following roadsL
1. New Jambutu-Ngolomba- Bogare (8.2km)
2. Njoboli- Njoboliyo Rugange (9.4km)
3. Labondo-Gwakrah-Koh-Goron-Borrong (34.6km)
4. Kwanan Waya-Namtari (4.2km)
The Lot 1 road is having the following villages and communities as beneficiaries: Bogare, Ngoromba, Jambutu and Ungwar Mai Rawani. Others are Njoboli-Rugange Road: Njoboliyo – River B T, Rugange. Also there is Labondo, Gwakrah-koh-Goron-Borrong Road. Wakawa, Gwagwara, Gari Hatsi, Gbogara Hasey, Yolde, Jikajam, Moron, Mbumara and Bange are all the villages that will be linked up and will run up to 56.4km access roads in the area.
RAMP-2 has equally extended to to Lot 2 of its roads project to the following roads currently on work:
1. Mildo-Muduvu-Madagali will be linking up with 14.9km road construction.
2. Kaya-Kuda-Bitiku-Sabon Gari will be having a 17.5km access road.
3. Shuwa-Pallam is another road that will run up to 8.1km.
4. Main Road-Koe-koppa will be receiving a 8.0km access road construction.
5. Bazza-Betso-Mango-Kalikasa-Zah is having 25km road construction.
These roads are having the following communities living along its corridor: Kaya, Kuda, Kubu, Bitiku, Giwamulu and Sabon Gari. Shuwa, Pallam, Mildo, Muduvu, Yibango, Masawa, Gambaro, Sukur and Madagali are also part of the benefitting communities.
Others are Bazza, Gwobeshi, Watsila, Shaffa, Mango, Bet so Mango, Saba, Mampe, Gwandum, Kalikasa, Bupa, Karaza, Karasa, Koe and Koppa.
Roads in Lots 3 that Ramp 2 will be doing are:
1. New Demsa- Old Demsa-Kodomun-Kwaine (28km)
2. Kpasham-Kebali-Yanga (15.2km)
3. Bille-Gumari-W/Hamawa-H/Bobbo-Gadamayo-M/Belwa (15.5km)
4. Gyawana-Hadiyo-Lamurde (12.8km)
Benefitting communities along Lot 3 are New Demsa, Old Demsa, Bwashi, Nogare, Kulero 1&2, Sabin Pegi, Kodomun, Pudde and Kwaine.
The roads will also have Kpasham, Kebali, Lawe, Yanga, Bille, Wuro Hamawa, Wuro Bobbo and MayoBelwa. Others are Gyawana, Pudde, Dubwangu, Goo, Mbemu, Hadiyo and Lamurde.
RAMP-2 is indeed geared toward making sure all rural communities are having good access roads and this is under the administration of Senator Muhammadu Umaru Jibrila Bindow. It will support the state in no distant time to change the entire Adamawa State with the good policy of: “Bindow for Social Change.”
Kudos to RAMP-2 as a Total of 201.4km roads is awarded to various communities in different local government area of the state by the stance effort of Adamawa State Government.
Trending
- Tinubu appoints renowned banker Jim Ovia as Chair of NELFUND
- Yahaya Bello: EFCC boss Olukoyede to face criminal trial for contempt of court
- President Tinubu appoint CEOs for two agencies
- Breaking: Veteran Yoruba actor, Ogunjimi is dead
- EX-PRESIDENT BUHARI MOURNS DEMISE OF SIDI ALI, DR. BAFFA YO
- Japa Crises: 58,000 of 130,000 registered doctors renewed licence, says MDCN
- 34-Km Ikorodu-Itokin Road Reconstruction: Gov Sanwo-Olu, Senator Abiru Pay Thank You Visit To Works Minister, Umahi, Make Case For Road Dualisation
- Yahaya Bello: EFCC Chairman’s conduct suggest vendetta, not fight against corruption – Concerned APC chieftains