The Federal Roads Maintenance Agency says the ongoing rehabilitation of a section of the Lagos-Badagry Expressway is 88 per cent completed.
FERMA South West 2 Zonal Coordinator, Rufus Onimisi, said this in an interview with the News Agency of Nigeria in Lagos on Thursday.
Onimisi said the project contractors were fast tracking construction on the project, which spans from Igboelerin to Agbara.
He said the project, which was earlier supposed to be completed in November 2020, was extended to April this year because the contractor lost a lot of time to the COVID-19 pandemic.
He said the project contractors, Wizchino Engineering Limited, had been doing night operations in order to complete the 24km project ahead of schedule.
Onimisi said that rehabilitation works had been done to final layer on about 22km and assured that the project would be delivered in March, a month ahead of schedule.
He said: “So far, we have done drainage works, kerb works, access culverts and work on the main carriageway.
“This comprises scarification, stone base, binder and wearing course and desilting works too, desilting of silted drainages.
“Right now, I can conveniently say the project is about 88 per cent completed.
“Drainage works completed is about 1.6km.
“The portion we are working on is 12km on each lane.
”So, the two carriageways is 24km out of which the asphalt we have done is about 11km on each lane, totaling 22km completed.
“At the rate at which rehabilitation works is going, I expect that by the end of March, we should be through with the project even though the project was extended to April.”
He added that within a fortnight, work would had been at the final stage or a level of just putting some minor finishing touches to the rehabilitation works.
Onimisi said although the high vehicular volume was affecting the construction, the commitment of law enforcement and traffic regulatory agencies helped to surmount the challenges.
The News Agency of Nigeria reports that three independent contractors are working on the highway under supervision of the Lagos State Government, FERMA and the Federal Ministry of Works and Housing.
The Lagos State Government is supervising work on the section from Eric Moore Road to Okokomaiko, while FERMA has jurisdiction over maintenance of the section from Igboelerin to Agbara.
The Federal Ministry of Works and Housing is supervising work from Agbara to Badagry.
NAN reports that the expansion of the Lagos-Badagry Expressway, a major gateway connecting Nigeria and neighbouring West African countries, was conceptualised in 2009 by the Babatunde Fashola Administration in Lagos State to ease traffic in the region and upgrade the infrastructure.