The Federal Government has terminated the contract for the concession of the Lagos-Ibadan Expressway with Bi-Courtney Limited.
The termination of the contract, worth N10 billion, was announced on Monday by the Minister of Works, Architect Mike Onolememen.
The minister said the termination followed the “serial breaching of the terms” of the contract by Bi-Courtney.
Prominent lawyer and businessman, Wale Babalakin (SAN), owns Bi-Courtney.
Onolememen also announced that the contract has now been awarded to the duo of Julius Berger Nigeria Plc and R.C.C. Nigeria Limited.
They are to commence work immediately, the minister said.
In a statement Onolememen read to State House correspondents, he said: “The Federal Government today, terminated the concession of the Lagos-Ibadan expressway granted to Bi-Courtney Consortium on 8th May, 2009.
“The termination of the concession agreement by Bi-Courtney consortium and especially the failure of the company to reach financial close as provided for in the agreement.
“Due to the senseless carnages on this important expressway which is part of Arterial Route A1, the Federal Government has also decided to embark on the emergency reconstruction of the expressway.
“Consequently, the Federal ministry of Works has engaged the services of Julius Berger Plc and R.C.C Nigeria Limited to commence work immediately on the reconstruction of the expressway.
“While Julius Berger would handle handle section 1: from Lagos to Shagamu interchange, RCC Nigeria Limited will be responsible for section II: from Shagamu to Ibadan.
“The Federal Government wishes to assure that while it will continue to uphold the sanctity of contracts entered into by the federal government, it will not shy away from implementing provisions of the contract agreement dealing with non-performance on the part of the contracting party.”
On the legal implication of terminating the contract, Onolememen said: “The legal implications of this termination have been carefully considered by both the Federal Ministry of Works and indeed the Federal Government.
“If you recall, we have been on this issue for quiet sometime now and we have meticulously followed the concession agreement, the provision of relevant clauses of the agreement.
“We have have complied fully with the provisions of this agreement.
“We have had cause even in the past to write the concessioner to detail the breaches which it had committed in this agreement in this particular transaction and we have also followed the minimum and maximum number of days the contractor was expected to remedy the situation but failing which the Federal Government had no alternative but to take this course of action.
“In terms of percentage payment so far, this is a concessioned project.
“In other words, it is different from the normal EPC contracts.
“So the Federal Government in a sense did not make any direct payment to Bi-Courtney in this particular transaction.
“Bi-Courtney was supposed to raise, he would have been able to raise the fund from the private sector and apply it to the construction of this expressway and toll it for as many as twenty five years, to recoup his investment and this has not happened, and that is why today the concession has been terminated.
“For your information, under this concession, the construction period is supposed to last for four years and the four years will come to a close in about six months time and right now there is nothing on ground to suggest that the company is capable.”
On whether it was a mistake giving the concession to Bi-Courtney he said: “I would not want to say that it was a mistake, because though I was not in the office as at that time, perhaps at that time they had the most responsible bids, the details is best known to the then minister of works and his team that handled the project.
“But again it is not out of place to give Nigerian companies opportunities to handle projects of this nature.
“This is our country.
“Whoever has the ability and the capacity to do projects of this nature we believe should encourage.”
On the percentage of work done on the road, the minister said: “I will leave that for those who use the road.
“As far as we are concerned, the terms of work has not been complied with.”
Trending
- Tinubu appoints renowned banker Jim Ovia as Chair of NELFUND
- Yahaya Bello: EFCC boss Olukoyede to face criminal trial for contempt of court
- President Tinubu appoint CEOs for two agencies
- Breaking: Veteran Yoruba actor, Ogunjimi is dead
- EX-PRESIDENT BUHARI MOURNS DEMISE OF SIDI ALI, DR. BAFFA YO
- Japa Crises: 58,000 of 130,000 registered doctors renewed licence, says MDCN
- 34-Km Ikorodu-Itokin Road Reconstruction: Gov Sanwo-Olu, Senator Abiru Pay Thank You Visit To Works Minister, Umahi, Make Case For Road Dualisation
- Yahaya Bello: EFCC Chairman’s conduct suggest vendetta, not fight against corruption – Concerned APC chieftains