The Federal Controller of Works in Lagos State, Adedamola Kuti, has said that traffic arrangements were underway to begin another phase of major repairs on the Third Mainland Bridge.
Kuti told the News Agency of Nigeria in Lagos on Sunday that results of investigative tests on the bridge were ready and contractors would move to site at the completion of the traffic management architecture.
He said: “Any moment from now, once I get our traffic plans approved, we may be announcing to the world again that we are now ready to fix Third Mainland Bridge, based on investigative tests we had last year.
“Meanwhile, we have already completed the resurfacing and the markings, such that you can now drive on Third Mainland Bridge smoothly.
“We are also going to repair some of the piles or pillars carrying the bridge; that is the next phase that we are doing.
“So work will soon begin on Third Mainland Bridge.”
Kuti said that the Muhammadu Buhari Administration was committed to fixing bridges in Lagos.
He said this was evident in the number of bridges that had been repaired in the state, with many more receiving attention.
He said: “This government has very good plans for bridges.
“Since I came on board, about a year ago, we have completed maintenance and repair works on Leventis Bridge, damaged by fire in 2016, where a whole deck collapsed.
“We have also completely repaired the Ijora-7Up Bridge.
“Coconut Bridge repair has been completed.
“The burnt Marine Beach Bridge repair has been completed and as I speak, maintenance work is ongoing on the Independence Bridge on the Island.
“Work is ongoing on the Dorman Long Bridge.
“You can drive smoothly on it now and all the guard rails and expansion joints are being replaced.
“Work is ongoing on the Ojuelegba Bridge as well as Alaka Bridge.”
According to Kuti, although procurement issues affected project delivery, there are enough materials from Alaka Bridge expansion joint works to repair adjoining bridges on the Apapa-Ijora axis.
The controller said he had given instruction to a contractor to move to site to rehabilitate a portion of the Apapa Bridge.
He said: “I have a project on the Alaka Bridge.
“Work is going on there.
“Alaka Bridge goes into Iganmu.
“The contractor has done a lot of work there.
“They have done the resurfacing, they have milled the old asphalt and are replacing the expansion joints.
“There is another expansion joint beside it.
“If you are coming in from Surulere and going to Alaka, the intersection is between Iganmu and Eko Bridge.
“I gave instruction to fix it.
“Also, at the intersection outwards Apapa and inwards Apapa from Costain area, there is a very bad expansion joint.
“I just gave instruction to fix it.”
Kuti added that expansion joints on the popular Long Bridge on the Lagos-Ibadan Expressway would also be replaced soon.
The controller, however, condemned illegal trading and other activities under bridges in Lagos, noting that some of such activities had caused fire and damaged bridges in the past.
Kuti similarly condemned indiscriminate parking on bridges, saying they were designed for movement of vehicles and not as parks.
Trending
- Beware of fake loan site, NELFUND warns students
- Police speak on video of allege massive traffic robbery in Abuja + Video
- Ms Courage (3), by Bassey Ubong
- Anti-corruption group demands access to Abia Forensic Audit Report
- Bello and Enenche: A tale of two lions, by Tunde Odesola
- Witch doctor impregnates wife of pastor who has been barren for 10 years
- AUN students protest over electricity blackout, management shifts exams
- Legit.ng’s EIC, TUKO.co.ke’s ME share newsroom growth insights