The Federal Government has kicked over the demand by the contractor handling the second runway project of the Nnamdi Azikiwe International Airport, Abuja for a N532 billion variation for an initial contract sum of N90 billion.
The Minister of Aviation and Aerospace Development, Festus Keyamo, made the position of the Federal Government known.
Keyamo stated this when he appeared before the National Assembly Joint Committee on Aviation to defend the ministry’s 2025 budget.
He said that the variation was against the initial N90 billion for the execution of the project.
The minister, while responding to a question on the reported stalled execution of the project, said the contractor had moved to site after the initial release of N30 billion and payment of compensation to communities on issues related to land.
Also Read:
- Judge adjourns proceedings in N228.4m forfeiture case against ex-Abia governor
- How agency banking is transforming financial access in developing countries, by Mxolisi Msutwana
- Ribadu slams Canada for denying military chiefs visa
- Worship For Change impacts thousands of children with special needs, donates N36.7m to six charities
- Tragedy as truck crushes female student to death in Bauchi
He said that the contractor had also done excavation on the site and carried out other works from the funds released and thereafter requested for a N532 billion variation.
This, he said, was unacceptable to the government.
Keyamo said: “The variation that the contractors are bringing is a variation that I totally disagree with.
“I will not go ahead with that variation.
“The President (Bola Tinubu) himself doesn’t like variation.
“If a contract was awarded for N90 billion, and they are proposing N532 billion variation within a space of two years, I will not accept it.
“The option I have is to cancel the contract.
“So, with the situation now, we have two proposals on the table, which I will take to the President, and I will consult my chairman.
“So we are considering various options.
“This country cannot go on with such unreasonable variations.”
The minister said that the ministry proposed a total of N71 billion in the 2025 budget, with capital projects put at N69 billion, personnel, N1 billion, while overhead was N745 million.
Keyamo said that a significant number of the projects listed for completion were already ongoing in the ministry.
Earlier, Chairman of the Joint Committee, Senator Abdulfatai Buhari, said that the committee must ensure efficient use of the funds allocated in order to achieve tangible results.
According to him, the committee will strengthen its oversight on the ministry and the firm spending the funds.
Buhari said that the projects were so important to the aviation sector.
He also said that the Nigeria Airspace Management Agency, which was removed from the Federal Government’s budget in 2023/2024, had been included in the 2025 budget.
“Therefore, this budget event will be a critical step in our efforts to ensure that our nation’s resources are allocated efficiently and effectively,” he said.
The senator commended the minister and his team for their commitment and the improvement recorded in the sector since the inception of the present administration.
He urged Keyamo to prevail on the agencies under the ministry to always respond promptly to invitations by the National Assembly.
He said that the national assembly had the power to invite the agencies in exercise of its oversight responsibility.
Buhari said: “The only thing we just want to take and appeal to you is your agencies, whenever we call them, we don’t want to issue a second warning, we don’t want a situation where we will call them and they won’t come.
“We have the power to invite them.
“So we want to appeal to you to appeal to your people that whenever they see a letter from the National Assembly, they should show up.”